New Project Timeline
I did get a hold of our other contractors who are going to install the kitchen cabinets. Installation date: April 18th. 2 1/2 weeks away. I thought they were going to be able to install much sooner. Now I’m going to revise my original project time line. It looks something like this:
- Finish with interior (Ellison’s Construction) 04.04.07
- Exterior Doors Installed (Ellison’s Construction) 04.06.07
- Carpet Floors in Family Room, Hallway, & Master Bedroom (Bixby Knolls Carpet) 04.07.07
- Exterior of House and Yard Completed (Ellison’s Construction) 04.16.07
- Kitchen Cabinets Installed 04.18.07
- Kitchen Counter Tops Installed 04.30.07
Now what I get to do tonight after work is once again move the 1,500lbs of cabinets from the family room onto the Kitchen tile so that the family room will be ready to be carpeted. Joy!
No related posts.
Related posts brought to you by Yet Another Related Posts Plugin.

